Milestones 

 

  Home

 

Sl.No.

Milestones

Target Date

1

Registration of Sethusamudram Corporation Ltd.

*06.12.2004

2

Submission of DPR to the Ministry

*01.03.2005

3

Appraisal by F.I. arranger

31/05/2005

4

Financial closure

30/06/2005

5

Approval of the competent authority

0 week

6

Pre-qualification and tender process (for dredging)

12 weeks

7

Award of work

16 weeks

8

Mobilisation of  Dredging equipment and pre-dredge survey

24 weeks

9

Commencement of dredging at Adams bridge area and Palk strait area

24 weeks

10

Preparation of designs, drawings and tender documents  for onshore facilities

26 weeks

11

Preparation of tender documents for procurement of Navigational aids, Port crafts

38 weeks

12

Call of tenders, pre-qualification process for procurement of Navigational aids and Port crafts & on shore facilities

50 weeks

13

Award of work for on shore facilities

56 weeks

14

Placing of supply orders for procurement of Navigational aids and Port crafts

62 weeks

15

Completion of procurement of Navigational aids and Port crafts

148 weeks

16

Completion of Service Jetties and Navigational towers

160 weeks

17

Completion of dredging work

166 weeks

18

Post dredging survey

168 weeks

19

Installation of VTMS

168 weeks

20

Commencement of Trials/ Tests

172 weeks

21

Commencement of Channel Operation

180 weeks