Sl.No.
|
Milestones
|
Target
Date
|
|
1
|
Registration
of Sethusamudram Corporation Ltd.
|
*06.12.2004
|
|
2
|
Submission
of DPR to the Ministry
|
*01.03.2005
|
|
3
|
Appraisal
by F.I. arranger
|
31/05/2005
|
|
4
|
Financial
closure
|
30/06/2005
|
|
5
|
Approval
of the competent authority
|
0
week
|
|
6
|
Pre-qualification
and tender process (for dredging)
|
12
weeks
|
|
7
|
Award
of work
|
16
weeks
|
|
8
|
Mobilisation
of Dredging
equipment and pre-dredge survey
|
24
weeks
|
|
9
|
Commencement
of dredging at Adams bridge area and Palk strait area
|
24
weeks
|
|
10
|
Preparation
of designs, drawings and tender documents
for onshore facilities
|
26
weeks
|
|
11
|
Preparation of tender documents for procurement of Navigational aids,
Port crafts
|
38
weeks
|
|
12
|
Call
of tenders, pre-qualification process for procurement of
Navigational aids and Port crafts & on shore facilities
|
50
weeks
|
|
13
|
Award
of work for on shore facilities
|
56
weeks
|
|
14
|
Placing
of supply orders for procurement of Navigational aids and Port
crafts
|
62
weeks
|
|
15
|
Completion
of procurement of Navigational aids and Port crafts
|
148
weeks
|
|
16
|
Completion
of Service Jetties and Navigational towers
|
160
weeks
|
|
17
|
Completion
of dredging work
|
166
weeks
|
|
18
|
Post
dredging survey
|
168
weeks
|
|
19
|
Installation
of VTMS
|
168
weeks
|
|
20
|
Commencement
of Trials/ Tests
|
172
weeks
|
|
21
|
Commencement
of Channel Operation
|
180
weeks
|