|
DPR
and Evaluation of EIA Study for
Sethusamudram Ship Channel Project
by
L&T Ramboll Consulting Engineers Limited,
339/340, Annasalai, Nandanam, Chennai-35

Executive
Summary
Top
Project
Background
India
has a peninsular coast of 3554 nautical miles and has had maritime
trade with various countries of the world since time immemorial.
Also shipping trade between the east and west coasts of
India
has prevailed for a long time.
But the coast of
India
does not have a continuous navigation channel connecting the east
and west coasts. Currently
the ships coming from the west coast of
India
and other western countries with destination in the east coast of
India
and also in
Bangladesh
, China etc. have to navigate around the
Sri Lanka
coast. The existing
waterway is shallow and not sufficient for the movement of ships.
This is due to the presence of a reef, known as
Adams
Bridge
, located south east of Rameswaram near Pamban,
which connects the Talaimannar Coast of Srilanka.
In
order to reduce the steaming distances between the east and west
coasts of India and to improve the navigation within the territorial
waters of India a number of proposals were considered to cut a ship
channel called Sethusamudram Ship
connecting the Gulf of Mannar with the Palk
Bay.
In
this context, Government of India appointed Tuticorin Port Trust
(TPT) as a Nodal Agency for developing the Sethusamudram
Ship Channel Project (SSCP) and entrusted the work of Preparation of
Detailed project report to L & T-RAMBOLL Consulting Engineers (LTR),
Chennai.
Top
Data
Collection and Review
As
many as nine pre independence proposals (between 1860 and 1922) were
formulated for cutting a Channel across the narrow strip of land
mostly through the
Rameswaram
Island
to connect the
Gulf of Mannar
with
Palk
Bay
. Post independence
proposals such as Sethusamudram Project
Committee – 1956; Nagendra Singh
Committee Report (1967) (C.V.Venkateswaran);
Lakshminarayana Committee
Report (1981); Pallavan
Transport Consultancy Services Report – 1996;
National Environmental Research Institute (NEERI)
Reports(2004) are reviewed and discussed in this report.
Top
Project
Site Environment
Sethusamudram
Ship Channel is proposed to be constructed connecting the
Bay of Bengal
to the
Gulf of Mannar
through a dredged channel on either side of the
Palk
Bay
.
The
nearshore to the western side of the
Rameswaram
Island
is found to be very shallow causing the Northeast monsoon waves to
break far offshore. The
coastal stretch in
Palk
Bay
shows the presence of wide beach with elevated dunes.
Data
shows that the climate along the entire length of the channel is
similar, with October to December being the rainy season, while May
to August is the hot season. However,
Adiramapatnam in the Palk
Bay received a substantial amount of rainfall during the months of
August and September, indicating that it is influenced by both the
NE and SW Monsoons Wind speeds are higher in June, July and August
during the SW monsoon, in which a significant percentage of the
observations are in the range of 8 to 10 m/s.
The analysis also shows most frequently occurring wind speed
class being 6-8 m/s. The
analysis also shows most frequently occurring wind speed class being
6-8 m/s during the NE monsoon in the months of November and
December. The
predominant wind directions are SW, WSW during Southwest and NE
during the Northeast monsoon seasons respectively and these
account for nearly 45% of the observations.
It
is observed that offshore wind speed in the vicinity of
Palk
Bay
exceeds 5 m/s for 76 days in a year while that exceeding 10 m/s is
only for 9.2 days.
In
about 150 years, a total of 44 storms (depressions, cyclones and
hurricanes) have passed within a radius of 200 km from Pamban
during the period 1842-1995, while the corresponding number around
Point Calimere is 60.
Most of the storms occur during the period October to
December, while there are no storms during the SW monsoon season.
The maximum reported wind speed is 130 knots, which is
estimated during the severe cyclonic storm of December 1964, which
is crossed close to Pamban.
From
the wave analysis of offshore data it is evident that off Palk
Straits, the waves are in the range of 0.5 to 1.8m with periods between
3 to 7s. During
the pre SW monsoon the waves are from SSE, SE and South directions
with annual percentage of 25%. However during the SW monsoon these
are predominantly from SSW, SW and West with annual percentage of
about 37%. Whereas,
during NE monsoon the predominant wave directions are NNE, NE and
ENE. The waves from
these directions cover 29% of the annual wave climate and 76% of the
wave climate during the NE monsoon (November – February).
The
tidal ranges of Rameswaram facing
Gulf of Mannar
, experiences a current in westerly direction throughout the year,
except in June and July. Although
the longside current was extremely weak
along the sand spit facing
Palk
Bay
, it tends to be easterly during Southwest monsoon/fair weather
period and westerly during Northeast monsoon.
The surface current velocities reported were as mild as 0.2
– 0.4 m/sec except on a few days during the south-west monsoon
when it rose upto 0.7 m/sec.
The directions of the currents were found to follow the
directions of predominant winds during the observations.
Top
Review
of Earlier Alignments
The
canal layout suggested by NEERI was reviewed from technical
requirements and to minimize dredging quantities and recommended
with minor changes to
geographical co-ordinates of turning points to minimize dredging
quantities and design of Channel bends as warranted from
navigational considerations.
Top
Field
Survey and Investigation
Field
measurements of waves and currents in the vicinity of the proposed
Channel are presented in the “Report on Sea state” prepared by
NSDRC. Wave data
collected using a wave rider buoy deployed off Vembar
in the
Gulf of Mannar
, for a period of one year during March 1997 to February 1998. This shows
Hs varies between 0.4 and 1.5m and Tz
varies between 3 and 9 sec.
Current
observations have been carried out at four locations, during three
seasons for a duration of two days in
each season.
Results
of the analysis shows that during SW monsoon, the average current
speed at the surface and bottom were 0.2m/sec with maximum being
0.3m/sec. During NW and
fair weather season average current values were 0.1m/sec.
Geotechnical
data to determine the nature of the soil parameters below the seabed
has been obtained at three locations in water depths of 2, 3 and 5m
in the Adams Bride area using jet probe drilling.
Suggestions
for further studies / Data collection
For
the purpose of preliminary design of the channel and to carry out
further studies to finalise the channel
alignment, design parameters in respect to the following Met –
Ocean parameters are essential.
-
Wind
speed and direction.
-
Wave
height, period and direction.
-
Current
speed and direction.
-
Tides
and Water levels.
In
order to arrive at reasonably accurate estimates of capital
dredging, it was suggested that the following additional surveys and
Investigations be carried out along the alignment of the channel.
-
Bathymetry
Survey
-
Sub
bottom profiling
-
Geotechnical
borehole investigation along the channel totaling up to 50
numbers.
-
A
comprehensive modeling exercise to study wave transformation and
breaking, flow pattern caused by breaking waves, tides and wing
and resulting sediment transport pattern be undertaken for both
the Adams Bridge region and the Palk
Straits region.
-
It
was also recommended to conduct a ship navigation simulation
study.
Field
Surveys and Model Studies Reports.
Tuticorin
Port Trust has since carried out Marine Geophysical Studies
(National Institute of Ocean Technology) and Mathematical Model
Studies (Indomer-Alkyon) in 2004-2005.
Tuticorin Port Trust also carried out Vibracrore
investigations at 44 locations along the channel alignment and 4
boreholes investigations at
Adam’s Bridge
. The finding s of these studies and investigations have
been discussed in this Report.
Top
Traffic
Forecast and Vessel size Analysis
GDP
method of traffic projection is considered appropriate as traffic of
SSCP is related to the growth of GDP for the country as a whole
rather than the developments in the immediate neighborhood of the
channel. Following methodology is adopted.
-
Questionnaire
survey
-
Study
trend in GDP
-
Traffic
study of major ports
-
Portwise
cargowise traffic projections for
all major ports using GDP method
-
Vessel
size analysis
-
Potential
Vessel traffic projection for SSCP
-
Restricted
Vessel traffic projection for SSCP
-
Checked
Vessel traffic projection with actual 203-04 data
A
detailed vessels size analysis has been carried out and typical
dimensions of the design vessel sizes are given below.
| Vessel
Size |
LOA
(m) |
Beam
(m) |
Draft
(m) |
|
30,000 |
190 |
30 |
10.5 * |
|
40,000 |
215 |
33 |
11.0 * |
|
50,000 |
267 |
33 |
12.5 * |
* draft restricted to 10 m
After
careful consideration of the channel parameters, it is recommended
to consider 10 m draft vessels to pass through the SSCP channel.
Even though the world-wide trend indicates the preference for
building larger vessels, there has been an increase about 5%
annually, in the number of vessels of size up to 30,000 DWT during
the last 20 years. Also, with this draft restriction of 10 m in the
SSCP, there could be a growth in number of ships specially built for
the purpose of passing through SSCP, may be called ‘SEHTU MAX’,
similar to vessels being built like Panamax
or Suez max vessels after the development of Panama and Suez canals.
From
the vessel size analysis, all vessels up to 20,000 DWT, about 75% of
30,000 DWT, 10% of vessels up to 40,000 DWT and 5% of vessels upto
50,000 DWT, and all empty vessels will fall in this category and can
pass through SSCP. This traffic is further adjusted to account for
downtime predicted by the model studies and is considered for
planning and financial analysis. Total traffic through SSCP is
presented in the table below:
| Year |
Pessimistic |
Moderate |
Optimistic |
| 2004 |
2344 |
2416 |
2490 |
| 2008 |
2858 |
3055 |
3249 |
| 2010 |
3140 |
3417 |
3683 |
| 2015 |
3900 |
4432 |
4895 |
| 2020 |
4784 |
5621 |
6343 |
| 2025 |
5883 |
7141 |
8234 |
Top
Preliminary
Design and Phasing
The
channel is designed as a two-way channel for the dimensions of
the design vessel, having a speed of 8 hnots.
The depth of channel is maintained at -12m CD and bottom width
of channel is 300m.
- By
adopting a minimum sight distance of 2.5km for the SSCP (same as
that of
Panama Canal
), minimum inter arrival time between ships required is 10
minutes (for vessel speed of 8knots). The inter-arrival time for
the year 2025, works out to 90 minutes, is well above this
minimum limit. So with two-way channel, the year 2025 traffic
can be handled without any congestion.
| Channel
Type |
Two
way |
| Channel
Width |
300m |
| Channel
Depth |
-12m
CD |
| Sight
Distance |
2.5
Km |
| Permitted
Draft of Vessel |
10m |
| Bean |
33m |
| LOA |
215m |
| Design
Speed |
8
knot |
Top
Identification
of Dredging Requirement
The
dredging quantity estimation is done taking sections at every 100m
interval and integrating over the length of segment. The details of
channel and dredging quantities computed for each segment are as
below.
| Segment |
Length
(Km) |
Dredge |
| Adam’s Bridge |
35
|
48.0
|
| Palk Bay |
78 |
No Dredging |
| Palk Strait |
54 |
34.5 |
| Total |
167 |
82.5 |
Based
on the model studies report, it is estimated the maintenance
dredging to be 2 million cu.m in the
first year reduction to 1.4 million cu.m
in 5 years and remaining constant thereafter.
For
dredging in
Adam’s Bridge
upto a level of (-) level, it is
proposed to deploy CSD. Dredging below the level of -8, upto
-12, will be by TSHD, except in region where dense / hard material
is encountered where again CSD will be used.
The
Palk Strait area is divided into two
sections depending on the distance to the dumping spot in Bay of
Bengal (one with average lead of 60 km and the other with average
lead of 40 km) where dredging will be carried out using TSHD.
The
dredged materials from
Adam’s Bridge
area is proposed to be dumped off-shore into sea in the
Gulf of Mannar
at location of 20-30 m natural depth within Indian territorial
waters. The dumping location is assessed to be 25-30 km away from
Adam’s Bridge
. The entire quantity of dredged material from
Adam’s Bridge
can be dumped at this site. As and option, about 8 million cu.m
is proposed to be used for degraded areas in Pamban
island.
The
dredged material from
Palk Strait
is proposed to be dumped offshore in
Bay of Bengal
area at about 25-30 m depth.
Top
Ancillary
Facilities
Buildings
: By the start of the
project and later on for administrative and operational purposes, an
administrative building complex having a plinth area of about
1000sq.m and field office complex of 500 sq.m
with amenities and security cabins are recommended at accessible
locations at Rameswaram / Pamban
/ Mandapam.
Service
Jetty :
Two service jetties one each at Dhanushkodi
and Point Calimere will be provided in
5m water depths.
Shore
Facilities
At
the root of service jetties on the reclaimed land, it is recommended
to construct the repair Workshop complex of 1000 m2 and
the Buoy Yard of 7500m2 with access facilities such as a
two lane road and railway sidings.
Development
of
Fishing
Harbour
The
fisheries
Harbour
at Rameswaram may be developed to modem
requirements with fish landing stations and augmenting shore
facilities for auctioning etc. as social development measure.
Two
more fishing harbours may also be
developed in the region, with the possible assistance of the State,
in identifying specific locations.
Top
Vessel
Traffic Management System and Navigational Aids
It
is recommended to provide VTMS for the SSCP operations. In view of
deeply dented coast with attendant range issues, provision
of 4 VTMS towers are minimum for reliable coverage. 4 number
RCC VTMS towers are provided with fittings and four floor
configuration to cover housing the VTMS equipment, microwave
communication link and tracking equipment, Channel Control Towers (CCTs),
AIS, Security, power supplies, meteorological and hydrological
instruments, and logistic needs. Two towers are located onshore at
Rameswaram
Island
and Point Calimere and two offshore
locations close to the Channel turning points in positions.
(D&E)
|
Sl.No
|
Item
|
Rameswaram
|
Point
Calimere
|
Off
shore platforms
|
|
1.
|
Heigh
(metres)
|
60
|
60
|
30
|
|
2.
|
Range
(NM)
|
19
|
19
|
13
|
|
3.
|
Radar
“S” band
|
Yes
- 2
|
Yes
- 2
|
Yes
– 1
|
|
4.
|
Radar
“X” band
|
Yes
- 2
|
Yes
- 2
|
Yes
– 1
|
|
5.
|
Integrated
VHF
|
Yes
- 2
|
Yes
- 2
|
Yes
- 2
|
|
6.
|
Integrated
HF commn
|
Yes
- 2
|
Yes
- 2
|
Yes
– 1
|
|
7.
|
AIS
|
Yes
- 2
|
Yes
- 2
|
Yes
- 1
|
|
8.
|
GSM
mobile commn
|
Yes
|
Yes
|
Yes
|
|
9.
|
Hydrographic
and Met. Equipment 60
|
Yes
- 2
|
Yes
- 2
|
Yes
- 1
|
The
navigational aids will play a crucial role for safe passage of
vessels through SSCP. The important navigational aids are as
follows.
(a)
VTMS
(b)
Navigational buoys as per IALA system-30
(c)
DGPS reference station at Rameswaram
and Point Calimere +2 Fairway buoys to
provide high and CCTs accuracy
positioning for vessels.
(d)
AIS (as per IMO SOLAS convention, regulation 19,
subsection 2.4.5) as part of VTMS
(e)
Set of legally valid navigational charts and
publications, based on detailed hydrographic surveys, for marine
safety, published by the National Hydrographic Office under IMO/IHO
conventions.
Flotilla
With
due regard to the navigational safety vis-ŕ-vis type of vessels and
weather conditions in the area, the minimum requirements are as
follows.
| Sl.
No |
Item |
Rameswaram |
Point
Calimere |
Offshore
CCT |
Total |
|
1. |
Tugs 30 Ton
Bollard Pull |
2 |
2 |
- |
4 |
|
2. |
Tugs 10 Ton
Bollard Pull |
1 |
1 |
2 |
4 |
|
3. |
Pilot Launch |
2 |
2 |
- |
4 |
|
4. |
Mooring Boats |
3 |
3 |
2 |
8 |
|
5. |
Survey launch |
1 |
- |
- |
1 |
|
6. |
Patrol Crafts |
2 |
1 |
2 |
5 |
|
7. |
Sullage
Barge |
1 |
- |
- |
1 |
|
8. |
Buoy servicing
Vessel |
1 |
- |
- |
1 |
|
9. |
Water Brage
(200 T) |
1 |
- |
- |
1 |
Note
: All SSCP crafts will have emergency support facilities and
10 Ton BP tugs will have oil pollution cleanup equipment.
Top
Environmental
and Social Impact Analysis
During
the year 2002, Tuticorin Port Trust (TPT) appointed National
Environmental Engineering Research Institute (NEERI), for carrying
out Rapid & Comprehensive Environmental Impact Assessment
Studies along with assessing Techno-economic viability,
Oceanographic Studies for the proposed Sethu
Samudram Ship Channel Project. (SSCP)
The
impacts predicted by NEERI were evaluated and subsequently an
Environmental Management Plan has been prepared in this Report. The
Environmental Management Plan covers the implementation &
operation phase of the SSCP.
The
impacts addressed by NEERI on environmental and social front and
also the impacts associated with the development of the land-based
facilities have been evaluated in this DPR for pre-construction,
construction and operation phase of SSCP.
|