Milestones 

 

  Home

 

Sl.No.

Milestones

Target Date

1

Registration of Sethusamudram Corporation Ltd.

*06.12.2004

2

Submission of DPR to the Ministry

*01.03.2005

3

Appraisal by F.I. arranger

31/05/2005

4

Financial closure

30/06/2005

5

Launching of Sethusamudram Corporation Limited Web Site

30/06/2005

6

Inauguration of Sethusamudram Project

02/07/2005

7

Approval of the competent authority

0 week

8

Pre-qualification and tender process (for dredging)

12 weeks

9

Award of work

16 weeks

10

Mobilisation of  Dredging equipment and pre-dredge survey

24 weeks

11

Commencement of dredging at Adams bridge area and Palk strait area

24 weeks

12

Preparation of designs, drawings and tender documents  for onshore facilities

26 weeks

13

Preparation of tender documents for procurement of Navigational aids, Port crafts

38 weeks

14

Call of tenders, pre-qualification process for procurement of Navigational aids and Port crafts & on shore facilities

50 weeks

15

Award of work for on shore facilities

56 weeks

16

Placing of supply orders for procurement of Navigational aids and Port crafts

62 weeks

17

Completion of procurement of Navigational aids and Port crafts

148 weeks

18

Completion of Service Jetties and Navigational towers

160 weeks

19

Completion of dredging work

166 weeks

20

Post dredging survey

168 weeks

21

Installation of VTMS

168 weeks

22

Commencement of Trials/ Tests

172 weeks

23

Commencement of Channel Operation

180 weeks

           *Actual dates

 Top             