   Project Implementation Schedule

 

           The Sethusamudram Ship Channel is proposed to be developed by a special purpose Vehicle (SPV) formed for this.

 

The entire construction (Including Captial dredging) would be through EPC contracts.  For timely completion of a large project like this, planning and implementation of various modules is important.

 

The implementation schedule is prepared and presented in the Figure.  Thus development is further divided into the following activities.

 

  • Pre Construction Activities

  • Construction Activities

Pre Construction Activities

 

Various activities identified under this heading are:

  • Submission of Detailed Project Report

  • PIB Clearance and other

  • Preparation of Tender Document

  • Tendering Process

Construction Activities

 

Various activities identified under this heading are:

 

a) Dredging

  • Duration of Contract (3 Years)

  • Preparatory Works

  • Site installation; site clearing for reclamation

  • Mobilisation of equipment

  • Dredging passage for Adam's Bridge

  • Dredging passage for Palk Strait

b) Procurement of Navigational Aids

  • Buoys

  • VTMS

c) Construction of Service Jetties & Shore facilities

 

d) Procurement of Port Craft

 

e) Trials/ Tests/ Commissioning

 

Dreding is the major activity in the development of the Channel, which is critical.  In this immplementation schedule, it is assumed that the whole of the dredging work will be carried out as a single contract with 2 fronts.  But this can be split up into two separate contracts, so that the construction period can be reduced by about 4 to 6 months.  But this will mean additional mobilisation and de-mobilisation, site installation, overhead and supervision /management costs, which will push the capital cost higher by 5 to 10%. 

 

Any further division of the project, into smaller contracts/ componenets, may not be economical as the additional costs mentioned in the earlier paragraph would be higher compared to the advantages of savings in project completion time and the resultant earlier start up of the project

 

Project Schedule

 

 

To view clear picture, open L&T DPR - Full Version and Go to Page No : 363

 