Project Status
|
Progress of Dredging Work
E ( Palk Bay/Palk Strait) E4
46.07 %
______ Total Dredging Quantity - 3,45,00,000 cum
______ Dredged Quantity - 15892962 cum till 10/10/2007
B (North of Adams Bridge) C
24.76 %
______ Total Dredging Quantity - 4,80,50,000 cum
______ Dredged Quantity - 11894810 cum till 17/9/2007
SETHUSAMUDRAM SHIP CHANNEL WORK PROGRESSING WELL AT PALK BAY - 10.73M ACHIEVED IN APRIL, 2008
|
||||||||||||||||||||||||||||||||